Client Name
City of Cape Town
Project Value
R8m
Project Completion
2021
Services
Design, Documentation, Construction, Monitoring
Project Description
The City Hall is situated in the Cape Town CBD and is a heritage building. As part of the project the HVAC installation and lifts were upgraded. The building is an existing facility consisting of 3 floors.
The air-conditioning installation consists of DX Split installations. New ventilation installations were also installed. Kitchen extract and bathrooms ventilation installations were installed.
The two old passenger/goods lifts were removed and new lifts installed.
Unique Features and Challenges
- HVAC systems had to be low noise. This had to be done in an existing building utilising existing plant rooms with very limited space
- Being an old heritage building, finding routes for all equipment was challenging